Some online services are currently unavailable
Some online services are currently unavailable. We are working to fix this as soon as possible. We are sorry for any inconvenience caused.
The purpose of EIA is to assess all potentially significant environmental impacts arising from a proposed development and to identify appropriate mitigation measures by which these impacts can be reduced or avoided. This ensures that local planning authorities take full account of the likely significant effects in determining planning applications. EIA is governed by the Town and Country Planning (EIA) Regulations 2011 as amended, which apply EU Directive 85/337/EEC “on the assessment of the effects of certain public and private projects on the environment” (the ‘EIA Directive’) to the planning system in England.
Before the Council can require a developer to prepare an EIA it must undertake ‘screening’ to determine whether the proposal is likely to have significant effects on the environment. If the proposed development is listed in Schedule 1 of the Regulations, an EIA is required in every case. If the proposed development is listed in Schedule 2 and exceeds the relevant exclusion thresholds and criteria set out in the second column, it must be screened having regard to:
Indicative size thresholds are provided in the third column of Schedule 2 to guide the screening process. Proposals located in, or partly in, a ‘sensitive area’ also need to be screened, even if they fall below the relevant thresholds.
Where a developer submits a request to the Council for screening opinion, the Council has 3 weeks within which to adopt its EIA screening opinion from the date on which the request was received (the 3 week period can be extended, if the developer agrees in writing to the extension). Once the Council’s screening opinion has been issued, it is required to be held on a public register.
Submissions should be emailed to developmentmanagement@sutton.gov.uk
Where a proposed development is determined to be ‘EIA development’, the developer can ask the Council for advice on the scope of the information to be gathered during the EIA and to be covered in the Environmental Statement (which reports on the findings of the EIA). The Council has a period of 5 weeks within which to produce an EIA Scoping Opinion, which can be extended if the developer agrees in writing to the extension. The planning authority is legally required to consult with the Environment Agency, Natural England, English Heritage and the Greater London Authority. Once the scoping opinion has been adopted, it is held in a public register.
Submissions should be emailed to developmentmanagement@sutton.gov.uk
Once an Environmental Statement has been submitted with a planning application, the Council can request additional information if it considers the Environmental Statement fails to address the minimum requirements set out in Schedule 3 of the EIA Regulations.
Further guidance in relation to EIA's can be found within the National Planning Practice Guidance.
Please view the Public register for detailed documents relating to EIA.
Help us improve our site by joining our user research panel